Published and reviewed 22 November 2026. General information, not advice. Figures are illustrations, not lender quotes.
The short version
- Land finance is borrowing by a business to buy land: a building plot or development site, land a company hopes to get planning permission on, a yard or open storage site, farmland, or land for a habitat bank. Most land purchases use a short-term bridging loan, a specialist land loan or the land advance in a development finance facility.
- Planning status sets the loan. Lenders that publish terms lend up to about 50% of value on land without planning permission, and roughly 60% to 75% once outline or full permission is in place. Together publishes up to 50% on land with or without planning from 9.24%, and Hope Capital launched a land bridge at 50% without planning from 0.99% a month.
- In our example, a developer’s company buys a 0.8 hectare site with outline permission for 14 homes for £1.1 million. A 65% bridge of £715,000 at 0.85% a month for 12 months pays out only £627,770 once interest and the fee are deducted. The company still needs about £600,000 of its own cash, or 55% of the price.
- The exit is the risk. If reserved matters approval comes three months late, the bridge costs about £25,400 more. If the site is valued 8% lower when the development lender takes over, the company must find about £107,800 to clear the bridge.
- Land is a soft market in late 2026. Savills says greenfield values fell 5.1% in the year to September and urban land 6.8%, and Knight Frank puts farmland at £8,442 an acre, down 3.1%. Bank Rate rose to 4% on 5 November 2026, and planning fees in England rise again on 8 December 2026.
What land finance is, and why lenders treat land differently
Land finance means the loans a business uses to buy land, hold it while it gets planning permission, or release money tied up in land it already owns. It covers a range of deals: a housebuilder buying a consented site, a company buying a field it hopes will be allocated for housing, a contractor buying a yard, an investor buying farmland, or a landowner refinancing a strategic site. This guide is written for UK limited companies borrowing for business purposes, which is the only kind of borrower our upcoming introduction service will work with.
Land is harder to borrow against than a building, for four reasons that run through the rest of this guide.
- It usually earns nothing. A let warehouse pays rent that covers the interest. A bare field earns little or nothing, so the lender is relying on the land’s value and on a plan to repay, not on income.
- Its value depends on planning. The same field can be worth £10,000 an acre as farmland and many times that with planning permission for homes. A lender that gets the planning call wrong can lose a large part of its money.
- It is slow to sell. Land often takes months to sell, and buyers are fewer when the housing market is weak. Valuers often give lenders a value assuming a sale within 90 or 180 days, which is lower than the full market value.
- The title can hide problems. Access, ransom strips, covenants, overage, tenancies, contamination and flooding all affect what land is worth. A building’s problems are usually visible. Land’s problems are often on paper.
What this guide covers
- Development land with outline or full planning permission, and the bridge from purchase to a development loan.
- Land without planning permission, including strategic land, options and promotion agreements.
- Commercial land such as yards, open storage, car parks and land next to your premises, financed with a term loan.
- Farmland and habitat banks, where specialist lenders lend over longer terms.
It does not cover buying a plot to build your own home, which is personal borrowing. A loan to an individual secured on land where they or their family will live can be a regulated mortgage contract under the FCA’s perimeter guidance, with different rules and protections.
The UK land market in late 2026: the numbers lenders start from
Lenders read the land market before they read your site. In late 2026 the picture is cautious. Land values are falling slowly, housebuilders are selling homes more slowly, and finance costs went up again in November. That does not stop land lending, but it makes valuers more conservative and lenders more interested in the exit.
| Measure | Figure | Source |
|---|---|---|
| UK greenfield residential land values, Q3 2026 | Down 2.0% in the quarter and 5.1% in the year. 13.3% below the 2022 peak | Savills, 28 October 2026 |
| UK urban residential land values, Q3 2026 | Down 1.7% in the quarter and 6.8% in the year. 19.9% below the 2022 peak | Savills |
| Scottish greenfield land values, year to Q3 2026 | Up 4.3% | Savills |
| New home sales rate | About 0.5 sales per site per week, from housebuilders’ trading statements | Savills |
| Average bare farmland value, England and Wales, Q3 2026 | £8,442 an acre, down 0.6% in the quarter and 3.1% in the year | Knight Frank Farmland Index |
| Farmland advertised for sale in 2026 to date | Just under 75,000 acres, almost 18% less than in 2025 | Knight Frank, citing the Farmers Weekly Land Tracker |
| Average bridging rate, Q3 2026 | 0.77% a month, the fourth fall in a row | MT Finance Bridging Trends |
| Average bridging loan to value, Q3 2026 | 59%, up from 55% | MT Finance Bridging Trends |
| Bank Rate | 4%, raised from 3.75% on 5 November 2026 | Bank of England |
Four messages come out of those figures. First, falling land values mean a lender’s valuer may put your site below the price you agreed, and the loan is based on the lower figure. Second, slow home sales make development lenders cautious about the schemes your land will become, which matters if your exit is a development loan. Third, bridging is cheaper than it was a year ago even though Bank Rate went up, because competition between bridging lenders is strong. Fourth, farmland is steadier than development land, with very little for sale. Knight Frank says prices are now at least 10% below the 2024 peak.
What changed for land buyers in 2026
- Interest rates. Bank Rate rose to 4% on 5 November 2026. Bank land loans and development loans priced over Bank Rate moved the same day. Most bridges are fixed for their short term, so an existing bridge does not change, but a new one or an extension may.
- Planning fees. Fees in England were raised by indexation on 1 April 2026 and rise again from 8 December 2026. An outline application for homes now costs £719 per 0.1 hectare on sites under 0.5 hectares and £896 per 0.1 hectare from 0.5 to 2.5 hectares. Full applications cost £752 per home for fewer than 10 homes and £818 per home for 10 to 49.
- Inheritance tax on farmland. From April 2026, full agricultural and business property relief for individuals is limited to the first £2.5 million of qualifying assets, with 50% relief above that. That changed who buys farmland, not how companies borrow, but it is one reason farmland values have softened.
Why planning status sets the loan
The single biggest factor in land finance is where the land sits in the planning process. Each step reduces the risk that the land will never be worth more than it is today, so each step increases what a lender will lend and lowers the rate. Here is how the stages work in England. Scotland, Wales and Northern Ireland have their own systems, with different names and timescales.
| Planning status | What it means | How lenders value it | Typical maximum loan to value |
|---|---|---|---|
| No permission, not allocated | The land has only its existing use, such as farming or grazing | Existing use value, with little or no allowance for hope | About 50%, or nil with some lenders. More with extra security |
| Allocated or promoted in a local plan | The council has identified the land for development, or a plan is being prepared | Existing use plus some hope value | About 50% to 60% with specialist lenders |
| Permission in principle | Agreement in principle to housing-led development, needing technical details consent before work starts | Part of the consented value | About 55% to 65% |
| Outline permission | Development agreed in principle, with reserved matters such as layout and appearance still to approve | Value with outline, discounted for the time and cost of reserved matters | About 60% to 70% |
| Full or detailed permission | All matters approved, subject to conditions | Full consented value | About 65% to 75%, or a development loan land advance |
| Permission implemented | Work has lawfully started, so the permission cannot expire | Full consented value | Usually refinanced into development finance |
The ranges come from published lender terms and specialist guides: Together publishes 50% on land with or without planning, Hope Capital launched its land bridge at 50% without planning, and bridging directories report up to about 75% with outline permission. They are a guide, not a promise. A lender uses the lower of the price and its valuer’s figure, and may cut the percentage for a remote site, a weak exit or an inexperienced borrower.
Permissions expire
Lenders check the dates on a permission, because a lapsed permission takes the value with it. Under section 91 of the Town and Country Planning Act 1990, a full permission usually lapses if work has not started within three years. Under section 92, an outline permission usually requires reserved matters applications within three years and a start within two years of the final approval. Councils can set different periods, so read the decision notice. If you are buying land with an old permission, find out whether it has been lawfully implemented before you agree a price.
How long planning takes
Councils should decide most applications within 8 weeks, or 13 weeks for major development, unless you agree a longer period. In practice, applications that need a section 106 agreement or raise objections often take longer. Permission in principle can be granted on application for minor housing schemes or through a council’s brownfield land register, but it still needs technical details consent before you can build. Build the realistic timescale, not the statutory one, into the length of any bridge.
Costs that come with permission
Planning permission brings obligations that a land buyer must price, because they reduce what the land is worth to a developer:
- Section 106 obligations, such as affordable housing and payments towards schools or roads, agreed with the council under planning obligations guidance.
- The Community Infrastructure Levy, a charge per square metre of new floor space in councils that have adopted it, payable when development starts. See the CIL guidance.
- Biodiversity net gain. Most development in England has had to deliver at least a 10% gain in biodiversity since 2024, on site, on other land or by buying units, under the biodiversity net gain rules. The government has consulted on easing the rules for small sites, so check the position when you apply.
- Nutrient and water neutrality. In some river catchments, new homes need mitigation before permission is granted. It can delay schemes and add cost per home.
The ways to finance a land purchase
Most land deals use one or more of these routes. Choose by the planning status, how long you will hold the land and how you plan to repay.
| Option | Best for | Typical term | How it is repaid |
|---|---|---|---|
| Bridging loan | Buying land quickly, at auction, or while you get or improve planning permission | 3 to 18 months, sometimes 24 | Development finance, a sale or a longer-term loan |
| Specialist land loan | Holding land for longer, with or without planning | Often 1 to 5 years, some longer | Monthly payments, a sale or a refinance |
| Development finance land advance | Buying land with full permission when you are ready to build | The build period plus a sales period, often 12 to 24 months | Sales or a refinance of the finished scheme |
| Planning gain or planning assistance loan | Improving an existing permission or securing a new one | Up to 12 months with some lenders | Development finance or a sale of the consented land |
| Term loan or commercial mortgage | Yards, open storage, car parks and land your trading business uses | 5 to 25 years | Monthly capital and interest from trading profit or rent |
| Agricultural mortgage | Farmland bought by a farming business | Up to 30 years with some lenders | Monthly or half-yearly from farm income |
| Option agreement | Securing land without buying it until planning is granted | Often 5 to 15 years | You buy the land, usually at a discount to its value with planning |
| Promotion agreement | A landowner who wants a promoter to fund and run the planning work | Often 5 to 15 years | The promoter takes a share of the sale price |
| Conditional contract | Agreeing a price now and completing only if planning is granted | Months to a few years | You complete, and finance, once the condition is met |
| Deferred or overage payment | Paying part of the price later, or sharing any planning uplift with the seller | Agreed in the contract | From the development or later sale |
Bridging loans
Bridging is the most common way to buy land, because it is fast and lent mainly against value and the exit rather than income. Interest is quoted per month and usually retained or rolled up, so nothing is paid monthly but the cash you receive is less than the loan. Our commercial bridging loans guide explains retained and rolled-up interest, open and closed bridges and extension terms in detail.
Specialist land loans
Some lenders offer land loans that run longer than a bridge, which suits land you will hold while a local plan is prepared. They tend to be priced higher than commercial mortgages and lend less. Together’s land mortgage, for example, publishes rates from 9.24%, up to 50% of value, and loans from £50,000 to £5 million, to companies or individuals, on land with or without planning. It says 100% is possible where extra property is offered as security.
Options, promotion agreements and conditional contracts
Many land deals avoid borrowing to buy unconsented land at all. Under an option agreement, a developer pays the landowner a fee for the right to buy the land within a set period, usually at an agreed discount to its market value once planning is granted. The developer pays for the planning application. Under a promotion agreement, a land promoter funds the planning work, then markets the consented land and takes an agreed share of the sale price. A conditional contract fixes the price now but completes only if planning is granted.
These structures move the planning risk off the lender’s balance sheet and limit the cash you have at risk to the option fee and the planning costs. The trade-off is that you do not own the land, so few lenders will fund the planning costs, and the landowner shares the uplift. We compare buying and optioning the same field below.
Deferred consideration and overage
Sellers sometimes agree to take part of the price later, or to accept a lower price now in exchange for overage, a share of any extra value if planning is granted within a set period. Overage is usually protected by a restriction or a charge on the title. A lender will want any deferred payment or overage to rank behind its loan, and will deduct it when sizing the loan if it does not.
What lenders publish in late 2026
Few land lenders publish full terms, and terms change often. These are the clearest published figures we found, with dates. They are examples of the market, not recommendations, and you should confirm current terms before relying on them.
| Lender or product | What it lends on | Published terms | Source and date |
|---|---|---|---|
| Together, land mortgage | Land with or without planning, including agricultural land, for commercial purposes | Up to 50% of value, £50,000 to £5 million, rates from 9.24%. Companies, individuals and non-UK residents | Together, viewed November 2026 |
| Hope Capital, land bridge | Land without planning permission | Up to 50% loan to value, from 0.99% a month, 3 to 18 months, minimum loan £150,000, no exit fee. Land with planning from 0.75% a month at launch | Mortgage Professional and launch release |
| Atom bank, Natural Capital loans | Buying or refinancing land in England to create biodiversity net gain units | £100,000 to £2 million, up to 65% of the original land value. Limited companies and LLPs only | Mortgage Solutions, 3 September 2026 |
| Shawbrook, Planning Assistance Loan | Sites with planning permission that the owner wants to improve | Up to 12 months, with an exit into Shawbrook development finance. Loan size and rates on application | Shawbrook, viewed November 2026 |
| Lloyds, Agricultural Mortgage Corporation | Farmland and farm businesses | Long-term loans over 5 to 30 years, with fixed rates available for up to 30 years | Lloyds Bank, viewed November 2026 |
| Bridging market average | All bridging, including land | 0.77% a month and 59% loan to value in Q3 2026 | MT Finance Bridging Trends, November 2026 |
Three points stand out. First, the published limits cluster around 50% for land without planning, which is far below the 70% to 75% bridging lenders offer on commercial buildings. Second, land loans are expensive by the standards of property finance. A rate of 9.24% a year or 0.99% a month compares with commercial mortgage rates closer to 6.5% to 8.5% for trading businesses. Third, lenders that fund land with planning often want to fund the development too. Shawbrook’s product is designed to lead into its development loan, and many bridging lenders offer a lower rate if you refinance with them.
What lenders want to see
- A clear exit. A planning timetable with a realistic decision date, a development appraisal or an agreed sale. Lenders ask who repays them and when, and test what happens if planning is refused.
- Your track record. Lenders lend more, and more cheaply, to companies whose directors have bought, consented or built similar sites before.
- Your own money in the deal. With 50% to 70% lending and costs on top, expect to put in at least a third of the total cost yourself, often more.
- Extra security. Where the land alone does not support the loan, a charge over other property can increase it. Lenders call this additional security.
- A personal guarantee. Most lenders to small and medium companies ask directors to guarantee the loan. Our guide to personal guarantees explains what that commits you to.
What land finance costs, beyond the rate
On a short loan the fees can add as much as the interest. Price every line, then add the cost of buying the land and getting it through planning.
| Cost | Typical level | Notes |
|---|---|---|
| Interest on a bridge | About 0.65% to 1.25% a month | Lower with full planning, a low loan to value and experience. Usually retained or rolled up |
| Interest on a land loan or term loan | About 7% to 11% a year | Banks lending to trading businesses sit at the lower end. Specialist land lenders higher |
| Arrangement fee | 1% to 2% of the loan | Usually deducted from the advance |
| Exit fee | Nil to 1.5% | Some lenders charge none. Check whether it is charged on the loan or the value |
| Valuation | About £2,000 to £6,000 for a typical site | Paid upfront and not refunded if the deal falls through |
| Lender’s legal fees | About £3,000 to £10,000 | Higher for complex titles, overage or options |
| Broker fee | Often up to 1% of the loan | Ask for it in writing before you proceed |
| Extension fee | Often 1% of the loan, plus more interest | Charged if you need longer than the agreed term |
| Default interest | Often 1% to 3% a month on top of the normal rate | Charged if the loan is not repaid on time |
The costs of buying the land
- Land tax. Bare land is charged at non-residential rates. In England and Northern Ireland, Stamp Duty Land Tax is 0% up to £150,000, 2% from £150,001 to £250,000 and 5% above. In Scotland, Land and Buildings Transaction Tax is 0% to £150,000, 1% to £250,000 and 5% above. In Wales, Land Transaction Tax is 0% to £225,000, 1% to £250,000, 5% to £1 million and 6% above. On £1.1 million that is £44,500 in England, £43,500 in Scotland and £43,750 in Wales.
- VAT, if the seller has opted to tax. A sale of land is normally exempt from VAT, but a seller who has opted to tax must charge 20%. Land tax is charged on the price including VAT. A VAT-registered buyer can usually reclaim the VAT, but must fund it until the refund arrives. If you intend to build homes, the option may not apply to your purchase, but the paperwork must be right before completion.
- Legal work and searches. Title checks, local authority, environmental, drainage and mining searches, and searches of the HM Land Registry title and plan.
- Surveys. Topographical, ecology and biodiversity baseline, ground investigation, flood risk, drainage, highways, trees and archaeology. Check long-term flood risk before you commission anything else.
- Planning costs. The application fee, architects, planning consultants and any technical reports the council asks for.
Worked example: a £1.1 million site with outline permission
Here is a purchase in pounds. All figures are illustrations, not lender quotes. A small housebuilding company, whose two directors have built four schemes of six to ten homes, agrees to buy a 0.8 hectare site on the edge of a market town in England. The site has outline permission for 14 homes, granted 14 months ago, with reserved matters still to approve. The price is £1.1 million, and the seller has not opted to tax.
The plan is to buy with a bridge, get reserved matters approved within 12 months, then repay the bridge with the land advance in a development loan.
The bridge
| Item | Figure |
|---|---|
| Loan | £715,000, 65% of the £1.1 million price, which the lender’s valuer supports |
| Rate and term | 0.85% a month for 12 months, interest retained |
| Retained interest | £715,000 × 0.85% × 12 = £72,930 |
| Arrangement fee at 2%, deducted | £14,300 |
| Cash actually received | £627,770, or 57% of the price |
| Owed at the end of month 12 | £715,000 |
Retained interest is why land deals need so much cash. The lender holds back a year’s interest at the start, so a 65% loan delivers only 57% of the price. If the interest were rolled up instead, the company would receive £700,700, but would owe about £787,930 at the end at simple interest, more if the lender compounds monthly, and the development lender would then need to lend that much on day one.
The cash the company needs
| Item | Amount |
|---|---|
| Purchase price | £1,100,000 |
| Stamp Duty Land Tax on £1.1 million at non-residential rates | £44,500 |
| Valuation | £4,500 |
| Lender’s legal fees | £6,000 |
| Own legal fees and searches | £9,000 |
| Broker fee at 1% | £7,150 |
| Reserved matters fee for 14 homes, at £818 per home from 8 December 2026 | £11,452 |
| Architect, surveys, ecology and biodiversity work for reserved matters | £45,000 |
| Total cost | £1,227,602 |
| Less cash received from the bridge | −£627,770 |
| Company’s own cash | £599,832 |
The finance alone costs £104,880: £72,930 of interest, the £14,300 arrangement fee, the valuation, the lender’s legal fees and the broker fee. That is 16.7% of the cash the bridge actually provides, or 9.5% of the price. Bridging is a short-term tool for a reason.
The exit
Once reserved matters are approved, the company applies for development finance to build the 14 homes. The development lender’s valuer puts the land, now with a detailed permission, at £1.2 million. Development lenders often advance 50% to 70% of land value on day one. At 60%, the land advance is £720,000, which repays the £715,000 bridge with £5,000 to spare. The rest of the development loan funds the build in stages. Our property development finance guide shows how that loan is sized against cost and gross development value.
The margin in that exit is thin, and that is typical. A bridge sized at 65% of today’s price relies on the land being worth more, or at least no less, when the development lender takes over.
Stress testing the land deal
Lenders ask what happens if planning or the market goes against you, so you should too. Three plausible problems:
- Reserved matters approval takes 15 months, not 12. A section 106 variation, a highways objection or a council backlog adds three months. The retained interest has run out.
- The site is valued 8% lower when the development lender takes over. Savills recorded a 5.1% fall in greenfield values in the year to September 2026, and secondary locations in the South East and East fell 15% to 20%. An 8% fall on the £1.1 million price gives £1,012,000.
- Both happen together.
| Scenario | What happens | Extra cash needed |
|---|---|---|
| As planned | Day-one land advance of £720,000 repays the £715,000 bridge | None. £5,000 to spare |
| Three months late | Three more months of interest at 0.85% (£18,233) plus a 1% extension fee (£7,150) | £25,383, unless the lender adds it to the loan |
| Value 8% lower | Land advance at 60% of £1,012,000 is £607,200, against a £715,000 bridge | £107,800 |
| Late and 8% lower | Both of the above | £133,183 |
| Late with no extension agreed | Default interest, often 1% to 3% a month extra, and the lender can enforce | Potentially much more |
A company that has already put in about £600,000 may not have another £130,000. There are four ways to build in room before you buy:
- Borrow less. At 55% the bridge would be £605,000. That needs about £95,000 more cash at the start but would be cleared by a 60% land advance even after an 8% fall in value.
- Agree a longer term. An 18-month bridge with interest retained for 12 months and the option to pay monthly after that avoids an extension fee. Many lenders charge interest only for the months you use, but check the minimum interest period.
- Make the purchase conditional on reserved matters. Exchanging conditionally and completing only once the details are approved removes the timing risk from the bridge altogether. Sellers often want a higher price or a non-refundable deposit in return.
- Line up the development lender first. Get indicative development terms, including the day-one land advance, before you complete the bridge. Some lenders offer a single facility that runs from land purchase to build.
Try your own figures. Multiply the bridge by the monthly rate and the number of months, add the fees, then work out what the development lender will advance on day one at a value 10% below your price. If the answer leaves a gap, you have found the cash you need to keep in reserve.
Strategic land: buying a field without planning, or taking an option
Land without planning permission is where the biggest gains, and the biggest losses, are made. Here is the same opportunity financed two ways. Again, all figures are illustrations.
A company wants 20 acres (8.1 hectares) of grazing land on the edge of a town. The council is preparing a new local plan and the land has been put forward for housing, but it is not yet allocated. The farmer wants £450,000, or £22,500 an acre, more than twice its value as farmland, because of its hope value.
Route one: buy it with a land bridge
| Item | Figure |
|---|---|
| Lender’s valuation | £300,000: £200,000 farmland value plus £100,000 of hope value the valuer will accept |
| Loan at 50% of the valuation | £150,000, which is only 33% of the price |
| Rate and term | 0.99% a month for 18 months, interest retained |
| Retained interest and 2% fee | £26,730 and £3,000 |
| Cash received | £120,270 |
| Stamp Duty Land Tax, valuation, legal and broker fees | £28,000 |
| Company’s own cash at completion | £357,730 |
| Outline application fee for 8.1 hectares from 8 December 2026 | £37,352 |
| Consultants, surveys and technical reports to outline, an assumption | About £160,000 |
| Total cash at risk before any planning decision | About £555,000 |
The lender values on what the land is worth today, not what you paid for the chance of planning, so the loan covers a third of the price. If the land is allocated and outline permission granted, the company can refinance or sell at a much higher value. If the council leaves it out of the plan, the field is worth about £200,000. The bridge still has to be repaid. A 50% land loan on £200,000 raises only £100,000, so the company must find another £50,000 or sell the land at a loss of more than £250,000 on its purchase.
Route two: take an option
Instead, the company pays the farmer £25,000 for a seven-year option to buy the land at 85% of its market value once outline permission is granted, less an agreed share of the planning costs. The company pays the same £197,000 of planning costs. If planning is refused, it has lost £222,000 and has no bridge to repay. On route one it would have spent about £555,000 and be left with a field worth about £200,000 and a £150,000 bridge, a loss of about £505,000. If planning is granted, it buys at a 15% discount and finances the purchase as consented land, at 60% to 70% rather than 50%.
The farmer keeps the land and most of the uplift, which is why landowners with good sites can choose between promoters. For the company, the option turns a property investment into a planning project, with far less borrowing. Few lenders will fund the planning costs on land you do not own, so this route needs equity, usually from the directors or an investor.
Habitat banks and other uses
Not every land buyer wants planning permission. Companies are also buying land to create habitat banks that sell biodiversity units to developers. Atom bank’s Natural Capital loans, launched in September 2026, lend £100,000 to £2 million to companies and LLPs for this, at up to 65% of the original land value, with flexible terms to fit irregular income from unit sales.
Commercial land: yards, open storage and land next to your premises
A trading business often needs land rather than a building: a contractor’s yard, open storage, lorry parking, a car park, or the plot next door to expand onto. If the land has an established commercial use and the business can repay from its profits, a term loan or commercial mortgage is usually cheaper than a bridge.
Here is an illustration. A groundworks company pays £36,000 a year to rent a 1.5 acre yard. It can buy a similar yard with an established storage use for £450,000.
| Item | Specialist land loan | Bank term loan to a trading business |
|---|---|---|
| Loan | £225,000, 50% of value | £292,500, 65% of value |
| Rate | 9.24%, Together’s published starting rate | 7.5%, an illustration of Bank Rate plus 3.5% |
| Term | 10 years | 15 years |
| Monthly repayment | £2,880 | £2,712 |
| Yearly repayments | £34,554 | £32,538 |
| Total interest if the rate stays the same | £120,541 | £195,572 |
| Stamp Duty Land Tax | £12,000 | £12,000 |
| Cash needed for the deposit, tax and costs | About £252,500 | About £185,000 |
Either way, the yearly repayments are close to the £36,000 rent, and the company builds up ownership of the land instead of paying a landlord. The bank route needs less cash, but banks lend on these terms mainly to established businesses with profits that cover the repayments comfortably, typically at least 1.25 times. Our owner-occupied commercial mortgages guide shows how that test works and compares renting with buying in pounds. Use the commercial mortgage calculator to try your own figures.
Check the use before you buy. Open storage often relies on a planning permission or a certificate of lawful use, and a yard used without one can face enforcement. Lenders will ask for the evidence.
Farmland bought by a farming business
Farming businesses usually borrow from banks with agricultural teams, over long terms that suit low yields. Lloyds’ Agricultural Mortgage Corporation lends over 5 to 30 years, with fixed rates available for the whole term. With bare farmland at about £8,442 an acre and rents far lower than interest costs, lenders look at the whole farm’s income and other assets, not the land alone. Our farm finance guide works through a 150-acre purchase by a farming company in pounds.
What lenders and their solicitors check on land
Most land deals that fail after the offer fail on title or survey problems. Lenders and their solicitors will check these points, so check them first.
- Access. Does the land have legal access to a public road for vehicles, wide enough for the planned use? A strip of land between the site and the road owned by someone else, called a ransom strip, can cost a large share of the uplift to buy.
- Rights and covenants. Rights of way, drainage and service easements, and restrictive covenants, such as a ban on building, can stop or limit development. Insurance can cover some old covenants.
- Overage and options. An earlier owner may be entitled to a share of any planning uplift. Lenders want overage postponed behind their charge.
- Tenancies and occupiers. Farmland may be let on a farm business tenancy or an older agricultural tenancy that can last a lifetime or pass to a successor. Lenders value land with vacant possession much higher.
- Ground and contamination. Former industrial or farm uses, landfill, mining and invasive plants such as Japanese knotweed all cost money to deal with.
- Flood risk and drainage. Land in a high flood risk zone is harder to get permission on and to finance.
- Utilities. Capacity in the local electricity, water and sewer networks. A new substation or a pumping station can cost hundreds of thousands of pounds.
- Ecology. Protected species, hedgerows, trees with preservation orders and the biodiversity baseline, which sets the gain a development must deliver.
- Boundaries. Whether the title plan matches what is on the ground. Title plans show general boundaries only.
Buy the reports before you exchange, or make exchange conditional on satisfactory results. A lender’s valuer will rely on them, and some will not value without them.
Tax points to settle before you borrow
Land tax, VAT and corporation tax can each change the numbers. Take advice on the specific deal, but settle these points before you agree a loan.
- Stamp Duty Land Tax and the devolved taxes. Bare land and farmland are charged at non-residential rates, as above. A purchase that includes a house as well as land is usually a mixed purchase, also charged at non-residential rates, but take advice if the house is the main part.
- VAT. Ask the seller early whether they have opted to tax. If so, budget for 20% VAT on the price, the land tax on it and the time to reclaim it, or the paperwork to disapply the option if you will build homes. Development land is often bought by a company that registers for VAT for the project.
- Trading or investment. If the company buys land to develop or sell, the profit is normally taxed as trading income. If it holds land as a long-term investment, a sale produces a chargeable gain. Either way, the corporation tax rate is 19% on profits up to £50,000, 25% above £250,000 and a tapered rate in between.
- Interest. Interest on borrowing for a company’s business is normally a deductible cost. For trading stock, such as land bought for development, finance costs are often added to the cost of the stock and relieved when the land or homes are sold.
- Community Infrastructure Levy. It is payable when development starts, not when you buy, but it reduces what a developer will pay you for consented land.
Applying: the pack, the timeline and the red flags
A complete pack gets faster and better terms. Expect lenders to ask for the following.
What to send
- The sale contract or heads of terms, the title and plan, and any option, overage or tenancy documents.
- The planning history: decision notices, conditions, section 106 agreements and the local plan position.
- A planning timetable and, if you will build, a development appraisal with costs, values and a downside case.
- Survey reports already available: topographical, ecology, flood risk, ground investigation and utilities.
- The exit: indicative development finance terms, a sale agreement or a refinance plan.
- Company accounts, a schedule of existing debt, and the directors’ experience, personal assets and liabilities.
- Proof of where your own money is coming from.
A typical timeline
- Agree heads of terms with the seller, ideally with time to complete your checks.
- Get indicative terms from two or three lenders, then pay for the valuation with the one you choose.
- The valuer inspects and reports, often within two to three weeks. The lender issues a formal offer.
- Solicitors check title and searches. Bridges on a clean title can complete in two to four weeks. Bridging Trends recorded an average of 41 days to complete in the third quarter of 2026.
- Exchange and complete, then start the planning work or the reserved matters application straight away.
Red flags lenders look for
- A price well above the valuer’s figure, especially for land without planning.
- An exit that depends on a planning decision with no realistic date, or on a local plan that has stalled.
- A permission close to expiry, or doubts about whether it has been lawfully implemented.
- No legal vehicle access, a ransom strip or a restrictive covenant against building.
- Sitting tenants or occupiers, or a farm tenancy with succession rights.
- A first-time developer seeking maximum lending with no partner or extra security.
- No cash left after completion to pay planning costs or interest if the term runs over.
Our commercial bridging loans guide explains how bridges are structured and repaid, and our guide to property development finance picks up where this one stops, when you are ready to build. Buying a building rather than bare land? See our guide to how to get a commercial mortgage.
Common questions
Can a company get a loan to buy land in the UK?
Yes. Most land purchases by companies use a bridging loan, a specialist land loan or the land advance in a development finance facility. Yards and land used by a trading business can often be financed with a term loan or commercial mortgage. How much you can borrow depends mainly on the planning status, the value and how you will repay.
How much deposit do I need to buy land?
Lenders that publish terms lend up to about 50% of value on land without planning permission and roughly 60% to 75% with outline or full permission. With fees, land tax and planning costs on top, expect to fund at least a third of the total cost yourself, and often half or more. In our £1.1 million example the company needs about £600,000 of its own cash.
Can you get finance for land without planning permission?
Yes, but from fewer lenders and on lower loan to values. Together publishes up to 50% on land with or without planning from 9.24%, and Hope Capital launched a land bridge at 50% without planning from 0.99% a month. Lenders value on the land’s existing use plus limited hope value, so the loan can be a small share of the price.
What interest rate will I pay on a land loan?
Bridges on land are typically about 0.65% to 1.25% a month in late 2026, with the market average for all bridging at 0.77% a month in the third quarter. Longer land loans run at about 7% to 11% a year. Bank Rate was 4% from 5 November 2026. Fees often add as much again on a short loan.
How long can a land loan last?
Bridges usually run for 3 to 18 months, sometimes 24. Specialist land loans often run for 1 to 5 years, and term loans on commercial land for 5 to 25 years. Agricultural mortgages can run for up to 30 years with some lenders, such as Lloyds’ Agricultural Mortgage Corporation.
Is land finance regulated?
Loans to a limited company for business purposes are usually not regulated by the FCA, so the facility letter is your main protection. A loan to an individual secured on land where they or their family will live can be a regulated mortgage contract, with different rules.
What is an option agreement on land?
An option gives a developer the right, but not the obligation, to buy land within a set period, usually at a discount to its value once planning permission is granted. The developer pays an option fee and the planning costs. It limits the money at risk if planning is refused, and avoids borrowing against unconsented land.
What happens if planning permission is refused?
The land is worth roughly its existing use value again, and any bridge still has to be repaid. In our strategic land example, a field bought for £450,000 is worth about £200,000 if left out of the local plan, leaving a gap the company must fund from its own money or by selling at a loss.
Do I pay stamp duty on land?
Yes. Bare land is charged at non-residential rates. In England and Northern Ireland, Stamp Duty Land Tax is 0% up to £150,000, 2% to £250,000 and 5% above, so £44,500 on £1.1 million. Scotland and Wales have their own taxes and rates. Land tax is charged on the VAT-inclusive price if the seller has opted to tax.
Is there VAT on land?
A sale of land is normally exempt from VAT, but if the seller has opted to tax it they must charge 20%. A VAT-registered buyer can usually reclaim it, but must fund it in the meantime. If you will build homes, the option may not apply to your purchase. Take VAT advice before exchange.
How do lenders value land?
A valuer looks at comparable land sales, the planning status and the cost of getting to a finished scheme. For development land they often work back from the value of the finished homes, deducting build costs, planning obligations, finance and profit. Lenders use the lower of the price and the valuation, and may use a value assuming a sale within 90 or 180 days.
How quickly can land finance complete?
A bridge on land with a clean title and a straightforward valuation can complete in two to four weeks. The Bridging Trends survey recorded an average of 41 days in the third quarter of 2026. Title problems, missing surveys and tenancies are the usual causes of delay.
Savills: Market in Minutes, residential development land, Q3 2026, 28 October 2026
Knight Frank: Farmland Index, Q3 2026
Mortgage Solutions: MT Finance Bridging Trends Q3 2026, 10 November 2026
Bank of England: Monetary Policy Summary, November 2026
MHCLG: fees for planning applications in England from 8 December 2026
The Intermediary: bridging lending rises 5% in Q3, MT Finance, November 2026
Mortgage Professional: Hope Capital bridging loan for land without planning permission
Hope Capital: land without planning permission bridge, launch release
Bridging Loan Directory: bridging finance on land
Mortgage Solutions: Atom bank launches loans for land converted into habitat banks, 3 September 2026
Shawbrook: Planning Assistance Loan
Lloyds Bank: Agricultural Mortgage Corporation
Town and Country Planning Act 1990, section 91
Town and Country Planning Act 1990, section 92
GOV.UK: determining a planning application
GOV.UK: permission in principle
GOV.UK: Community Infrastructure Levy
GOV.UK: understanding biodiversity net gain
GOV.UK: inheritance tax reliefs threshold to rise to £2.5 million for farmers and businesses
GOV.UK: SDLT non-residential and mixed rates
Revenue Scotland: Land and Buildings Transaction Tax, non-residential property
Welsh Government: Land Transaction Tax rates and bands
HMRC: opting to tax land and buildings (VAT Notice 742A)
GOV.UK: Corporation Tax rates and reliefs
GOV.UK: search property information from HM Land Registry
GOV.UK: check long-term flood risk
FCA Handbook: PERG 4, regulated mortgage contracts
Rates, tax bands and lender criteria change. Confirm the current details with the lender, your solicitor or your accountant before relying on them.