Property development finance: how it works and what it costs

Build it right.
Fund it in stages.

How UK development finance works, from loan to cost and GDV limits to 2026 rates, fees and drawdowns. Includes the planning and tax costs appraisals miss, a worked six-unit scheme, stress tests and a mezzanine comparison.

Illustration of two business owners talking through plans at a table

Published and reviewed 27 October 2026. General information, not advice. Figures are illustrations, not lender quotes.

The short version

  • Development finance is a short-term loan for building new property or carrying out a major conversion. It is released in stages as the work is done and checked by a monitoring surveyor. Interest is usually added to the loan rather than paid monthly, and everything is repaid when the finished property is sold or refinanced.
  • Lenders cap the loan twice: at a share of the total cost, often 75% to 90%, and at a share of the gross development value (GDV), the finished value, often 60% to 70%. The lower figure applies. The developer funds the rest, usually 10% to 25% of costs, and any overruns.
  • Senior development loans are typically priced at about 0.65% to 1.1% a month in October 2026, or roughly 8% to 13% a year, plus an arrangement fee of 1% to 2%, an exit fee of up to about 1.5%, valuation, legal and monitoring costs. Bank Rate is 3.75%.
  • In our worked example, six light industrial units costing £1.98 million to build and selling for £2.7 million make about £440,000 before tax, 16.3% of GDV, after about £199,000 of finance costs. A 10% build overrun, a three-month delay and prices 7.5% lower together cut that to about £63,000.
  • Appraisals most often go wrong on the costs around the build: CIL, section 106, biodiversity net gain, VAT cash flow, utilities and, for tall residential buildings, Building Safety Regulator approval times. Price them before you buy the site.

What is development finance?

Development finance is a short-term loan used to build new property or substantially change an existing building. It funds work that a normal mortgage lender will not, because there is nothing finished to lend against yet. Typical projects include:

  • Ground-up new build: houses, flats, industrial and trade units, offices, care homes or student accommodation on a cleared site.
  • Conversions: an office or shop turned into flats, a barn into homes, or a large house into a block.
  • Heavy refurbishment: structural work, extensions or a change of use that needs planning permission and building regulations approval.

Three features set it apart from other business borrowing. The money is released in stages, in arrears, as each part of the build is completed and certified. Interest is usually rolled up, added to the balance and paid at the end, because the site earns nothing while it is being built. And the loan is repaid in one go from the exit: the sale of the finished property, or a longer-term loan once it is let.

Lighter work, such as cosmetic refurbishment that needs no planning permission, is usually funded with a commercial bridging loan instead. Our guide to commercial loans shows where development finance sits among the other types of business property finance.

Our upcoming introduction service is limited to UK limited companies and excludes residential-property security, so it would cover commercial schemes such as industrial units, offices and retail, but not loans secured on homes or flats. This guide explains both, because most of the principles are the same. It assumes the borrower is a limited company, usually a special purpose vehicle (SPV) set up for the project.

How development finance works, step by step

A development loan follows the project from the site purchase to the sale of the last unit. Each stage has its own checks.

  1. Appraisal. You set out the site cost, build cost, fees, contingency, finance cost, the finished value and the profit. Lenders judge the scheme first on this document.
  2. Terms. A lender or broker issues indicative terms: the facility size, rate, fees, the share of the site it will fund and the conditions.
  3. Valuation. The lender instructs a RICS valuer to report on the site value today and the GDV, often with a view on the build cost and how quickly units will sell.
  4. Monitoring surveyor’s initial report. A quantity surveyor acting for the lender reviews the build contract, the cost plan, the programme, planning and the professional team.
  5. Credit approval and legal work. Solicitors for both sides deal with title, security, the build contract, warranties, insurance and any guarantees.
  6. Day-one advance. At completion of the site purchase, the lender releases its agreed share of the site cost. Your equity goes in first or alongside.
  7. Monthly drawdowns. The monitoring surveyor visits, values the work done and certifies it. The lender pays the contractor or the developer for the certified work, usually within a few working days.
  8. Practical completion. The building is finished, signed off by building control and, for new homes, covered by a structural warranty.
  9. Exit. Sale proceeds go to the lender until the loan, interest and fees are repaid. Or the property is let and refinanced onto a term loan.
Typical timescales for development finance
StageTypical timeWhat can slow it down
Indicative termsA few days to 2 weeksAn incomplete appraisal or no build cost evidence.
Valuation and initial report2 to 4 weeksUnusual schemes, few comparable sales, an unpriced build contract.
Credit approval1 to 3 weeksA first-time developer, a weak contractor or thin profit.
Legal work3 to 6 weeksTitle problems, pre-commencement planning conditions, third-party consents.
Application to first drawdownUsually 6 to 12 weeksLeave longer if the site purchase depends on it.

Interest is only charged on money that has been drawn, which keeps the cost down early in the build. Some lenders also charge a small non-utilisation fee on the undrawn part of the facility.

How much can you borrow? Loan to cost and GDV

Development lenders size a loan against two limits and use whichever is lower.

  • Loan to cost (LTC): the loan as a share of the total project cost, usually the site, the build, professional fees and contingency. Senior lenders commonly go to 75% to 90% of costs.
  • Loan to gross development value (LTGDV): the loan as a share of the finished value. Senior lenders commonly go to 60% to 70% of GDV. For a gross loan cap, the fees and the rolled-up interest count towards this limit, not just the money you receive.

Lenders usually fund the build in full, in arrears, and only part of the site. A common pattern is 50% to 70% of the site price on day one, with the developer’s money going in first. The less profit the scheme makes, the more the LTGDV cap bites and the smaller the share of the site the lender can fund.

Worked example: which limit applies?

A scheme costs £2,000,000 before finance and will be worth £2,700,000 when finished. The lender offers up to 85% of costs and up to 65% of GDV, gross of fees and interest.

  • 85% of costs: £1,700,000.
  • 65% of GDV: £1,755,000 gross. After an assumed £150,000 of fees and rolled-up interest, about £1,605,000 is left for the site and the build.

The GDV cap applies. The lender funds about £1,605,000, roughly 80% of costs, and the developer finds the other £395,000. The figures are illustrations, not a lender quote.

Typical borrowing limits by type of development finance
Type of financeTypical limitWhere it sits
Senior development loan60% to 70% of GDV, 75% to 90% of costsFirst charge over the site. Repaid first.
Stretched seniorUp to about 75% of GDV, up to 90% of costsOne first-charge loan at a higher rate, replacing senior and mezzanine.
MezzanineTotal debt up to 75% to 85% of GDV, 90% to 95% of costsSecond charge, repaid after the senior lender.
Equity or joint ventureUp to all of the developer’s sharePaid from profit, after all lenders.
Land or pre-planning loan50% to 65% of the current site valueUsually a bridging loan. Planning gain is not lent against until permission is granted.
Development exit loanUp to about 70% to 75% of GDVReplaces the development loan at or near completion, while units sell.

These ranges are drawn from published lender and broker information for UK schemes in October 2026. They are not offers, and many lenders go lower for first-time developers or unusual property. Our guide to how much a business can borrow explains how lenders size other kinds of loan.

Development finance rates and fees in 2026

Development finance is priced mostly as a monthly rate, with a set of fees on top. The Bank of England held Bank Rate at 3.75% on 17 September 2026, and its next decision is due on 5 November 2026. Banks often price development loans as a margin over Bank Rate or SONIA. Specialist lenders usually quote a fixed monthly rate for the life of the loan.

Indicative development finance costs for UK schemes, October 2026
CostTypical rangeHow it is charged
Interest, senior loanAbout 0.65% to 1.1% a month, roughly 8% to 13% a yearOn the drawn balance, usually rolled up and paid at exit. Experienced developers on residential schemes see the lowest rates. Commercial and first-time schemes are usually priced higher.
Interest, mezzanineAbout 1.25% to 2% a month, sometimes with a profit shareRolled up and repaid after the senior loan.
Arrangement fee1% to 2% of the facilityUsually added to the loan on day one, so you pay interest on it.
Exit fee0% to about 1.5%A percentage of the facility or of the GDV. A fee on GDV is much larger, so check which.
Broker feeOften 0.5% to 1% of the facilitySome brokers are paid only by the lender. Ask before you instruct one.
ValuationFrom a few thousand pounds on a small schemePaid upfront. Larger or unusual schemes cost more.
Monitoring surveyorAn initial report, then roughly £1,000 to £1,500 a visitUsually monthly, for the length of the build.
Lender’s legal feesOften £5,000 to £15,000 or morePaid by the borrower, whether or not the loan completes.
Extension or default feesOften a higher rate plus a feeCharged if the loan runs past its term. A key risk if sales are slow.

These ranges are indicative, drawn from published lender and broker information for October 2026. They are not quotes. A monthly rate compounds when interest is rolled up: 0.95% a month is 11.4% a year before compounding, and about 12% after it. Compare offers on the total cost in pounds over your expected programme, including fees, not on the headline rate. Our guides to business loan interest rates and comparing business loans explain how to put different quotes on the same basis.

Types of development finance compared

Most schemes are funded by a senior loan plus the developer’s own money. When the developer has less cash, another layer fills the gap, at a price.

Types of property development finance
OptionWhat it isSuitsWatch out for
Senior development loanA first-charge loan for the site and the build, drawn in stages.Most schemes with full planning and a clear exit.The developer funds 10% to 25% of costs and any overruns.
Stretched seniorOne loan to a higher share of costs, at a higher rate.Developers who want one lender and less equity in.Fewer lenders, tighter checks on experience.
MezzanineA second loan behind the senior lender, to cut the equity needed.Strong-profit schemes where cash is the constraint.Expensive. It comes off your profit and makes losses bigger.
Equity or joint ventureAn investor puts in most or all of the developer’s share for a share of the profit.Experienced teams with good sites but little capital.You may give up half the profit, and some control.
Land or pre-planning bridgingA short loan to buy a site before or while seeking planning.Buying a site quickly or before planning is granted.Lent on today’s value, not the value with planning. Planning risk is yours.
Refurbishment bridgingA bridging loan that also funds lighter works.Light or medium refurbishment, including some permitted development conversions.Usually not suitable for new build or heavy structural work.
Development exit loanA cheaper loan that repays the development loan when the build is finished.Schemes where sales or lettings will take months.Only works if completion is signed off and the valuation holds.
Bank or public lenderHigh-street banks, regional lenders and, in England, the National Housing Bank.Experienced developers, larger schemes and some SME housebuilders.More paperwork, lower leverage and longer approval times.

In England, the National Housing Bank, set up by Homes England in March 2026, offers loans, equity and guarantees for housing delivery, including for smaller housebuilders. It works alongside private lenders rather than replacing them, so most SME schemes are still funded by banks and specialist lenders.

When a scheme has a buyer lined up, or will be held and let, the exit matters as much as the build loan. Owner-occupiers who buy finished commercial units often use a commercial mortgage. A developer that keeps and lets the units usually refinances onto a commercial investment loan. Our guide to commercial buy to let mortgages explains the rent cover that refinance needs.

What development lenders look for

A development lender is betting that the building gets finished, on budget, and sells or lets for what the valuer expects. Everything it asks for tests one of those three things.

The scheme

  • Planning. Full planning permission, ideally with the pre-commencement conditions discharged. A permission usually has to be started within 3 years of being granted, so lenders check the date. Some conversions use permitted development rights with prior approval instead.
  • Profit. Many lenders want a profit of at least 15% to 20% of GDV, or 20% to 25% of cost. A thinner margin leaves no room for overruns.
  • Evidence of value. Recent sales or lettings of similar property nearby, and agents’ views on price and how fast it will sell.
  • A priced build. A detailed cost plan, a programme and, ideally, a fixed-price contract.

The team

  • Your track record. Completed schemes of a similar type and size. Lenders are more comfortable when the new scheme is a step up, not a leap.
  • The contractor. Its accounts, insurance and experience. Many lenders prefer a recognised fixed-price contract, such as a JCT design and build contract, with a contractor that will survive the build.
  • The professional team. Architect, structural engineer, quantity surveyor, project manager and building control, appointed with professional indemnity insurance. Lenders usually ask for collateral warranties so they can rely on the team’s work.

The borrower and the money

  • A clean SPV. Many lenders prefer a limited company set up only for the project, with no other trading history or debts. Common SIC codes are 41100, development of building projects, and 68100, buying and selling of own real estate.
  • Your equity. Proof of where your share of the costs comes from, and that it is in the scheme before the lender’s money.
  • Guarantees. Personal guarantees from the directors are normal on SME schemes, sometimes capped at part of the loan, and some lenders also ask for cost overrun and completion guarantees. Our guide to personal guarantees explains what you would be signing.
  • Credit history. The company’s and directors’ records. Our guide to bad credit business loans explains how lenders weigh CCJs and defaults.

Lending to a limited company to build property for sale or letting is not a regulated mortgage contract, so FCA mortgage rules do not apply. The FCA’s perimeter guidance sets out when property lending is regulated. That leaves the detail of the facility letter to you and your solicitor, so read it in full.

Planning, tax and the costs appraisals miss

Build cost gets the most attention, but the costs around it are what most often turn a profitable appraisal into a thin one. Lenders will expect each of these to be priced.

Community Infrastructure Levy (CIL)

In areas that charge it, CIL applies to most new development that creates 100 square metres or more of new floorspace, or a new home, at a rate per square metre set locally. Rates vary widely by area and use, and many councils zero-rate some commercial uses. Under the government’s CIL guidance, someone must assume liability and the council must receive a commencement notice before work starts. Miss that and the full amount can become payable at once, without the council’s instalment policy, and surcharges can apply.

Section 106 and highway works

Planning obligations can require affordable housing, payments towards schools, open space or transport, or highway works. Under the planning obligations guidance, affordable housing should only be sought on major residential development, generally 10 or more homes or a site of 0.5 hectares or more. Smaller schemes can still face other contributions.

Biodiversity net gain (BNG)

In England, most planning permissions must deliver a 10% gain in biodiversity, on site, off site or by buying credits. From 6 August 2026, developments on sites of 0.2 hectares or less are exempt, unless they affect priority habitat, and the separate self-build exemption no longer applies to new applications. Larger sites need an ecologist’s assessment early, because off-site units can cost tens of thousands of pounds.

Stamp Duty Land Tax on the site

Land with no dwelling on it is charged at non-residential rates: nothing up to £150,000, 2% to £250,000 and 5% above. A site bought for £380,000 costs £8,500. Buying a house to demolish or convert is a residential purchase. Companies pay a 5% surcharge on residential property and, above £500,000, can face a flat 17% rate, although relief from the 17% rate may be available to property developers that meet the conditions. Scotland and Wales have their own taxes.

VAT

VAT changes both the cost and the cash flow, and it differs by type of scheme. Under VAT Notice 708, building new homes is zero-rated, and converting a non-residential building into homes is charged at 5%. New commercial buildings are standard-rated at 20%, and a freehold sale of a commercial building within 3 years of completion is also standard-rated. A developer that registers for VAT can usually recover the VAT it pays, but it has to fund that VAT until the refund arrives. On £1.5 million of commercial build costs and fees, that is about £300,000 passing through the company. Some lenders offer a separate VAT facility. If the seller of a site has opted to tax, VAT is added to the price and SDLT is charged on the VAT-inclusive figure. Take advice from an accountant before you exchange.

Utilities, warranties and building safety

  • Utilities. New connections, diversions and, for industrial schemes, an electricity supply upgrade or substation can cost far more than expected and take months. Get quotes before you buy.
  • Structural warranty. Buyers’ mortgage lenders generally expect new homes to carry a 10-year structural warranty, and developers registered under the New Homes Quality Code have duties to buyers. Commercial schemes rely more on collateral warranties.
  • Higher-risk buildings. Buildings of at least 18 metres or 7 storeys with at least 2 homes need Building Safety Regulator approval before work starts. The regulator aims to decide new-build applications within 12 weeks, but its May to July 2026 data shows a median of 22 weeks. A lender will price that wait into the programme and the interest.

Worked example: six light industrial units

This example follows a commercial scheme from site to sale. The figures are assumptions for the illustration, not a lender quote or a valuation.

Worked example: the appraisal

A developer’s new SPV buys a 0.3 hectare site in England with full planning for six light industrial units of 200 square metres each, 1,200 square metres in all. The build takes 10 months. Two units are pre-sold to local businesses, and the agents expect the other four to sell over the following four months at £450,000 each.

Development appraisal for six light industrial units
ItemAssumptionCost
SiteAgreed price, no VAT charged£380,000
SDLTNon-residential rates£8,500
Acquisition legal fees and surveysEstimate£7,500
Build cost1,200 m² at £1,050 per m², including yard and externals£1,260,000
Professional fees10% of build cost£126,000
Contingency5% of build cost£63,000
Utilities and power upgradeQuotes from the network operator£60,000
Biodiversity net gainOff-site units, as the site is over 0.2 hectares£30,000
Section 106 and highway worksUnder the planning agreement£45,000
CILZero-rated for industrial use in this council’s charging schedule£0
Total cost before financeAll of the above£1,980,000
GDVSix units at £450,000£2,700,000
Sales costsAgents and legal fees, 3% of sales£81,000

VAT on the build is left out because the developer registers for VAT and recovers it. It still has to fund about £300,000 of VAT until each refund arrives.

Worked example: the funding

A specialist lender offers a facility of up to 65% of GDV, gross of fees and interest, which is £1,755,000. The rate is 0.95% a month, rolled up, with a 2% arrangement fee (£35,100) and a 1% exit fee (£17,550). The lender funds the build, fees, contingency and utilities in full, in arrears, and as much of the site as the 65% cap allows.

  • Lender’s money: £115,000 towards the site, about 30% of the price, plus £1,509,000 for the build, fees, contingency and utilities. That is £1,624,000, about 82% of costs.
  • Developer’s money: the other £265,000 of the site, SDLT, acquisition costs, BNG and section 106, plus the lender’s valuation (£6,000), legal fees (£10,000) and the monitoring surveyor’s initial report (£2,500). That is £374,500, about 19% of costs.
  • The peak: with fees and interest rolled up, the loan peaks at about £1,754,800 at practical completion, just inside the £1,755,000 cap.
Finance costs and profit for six light industrial units
ItemAmount
Rolled-up interest over 15 monthsAbout £113,800
Arrangement and exit fees£52,650
Valuation, lender’s legal fees and monitoring£32,250
Total finance costAbout £198,700
Total cost, including finance and sales costsAbout £2,259,700
Profit before Corporation TaxAbout £440,300
Profit on GDV16.3%
Profit on cost19.5%

The pre-sold units and sale proceeds repay the lender first. The loan is cleared when the fifth unit sells, 14 months in, and the sixth sale goes entirely to the developer. On £374,500 of its own money, the SPV makes about £440,300 before tax over 15 months. Profits above £250,000 are taxed at the 25% main rate of Corporation Tax.

A profit of 16.3% of GDV is near the bottom of what many lenders accept. That is why the next step, the stress test, matters.

Stress-testing the scheme: what if it goes wrong?

A lender will run its own downside cases, and so should you. Here is the same scheme with the things that most often go wrong. Each case uses the same facility as above.

Stress test of the six-unit scheme
ScenarioProfit before taxProfit on GDVWhat it means
Base caseAbout £440,30016.3%As appraised.
Sales three months laterAbout £387,80014.4%About £52,500 more interest. The rolled-up balance overshoots the facility by about £51,600, which the developer must pay in.
Sale prices 10% lowerAbout £174,6007.2%GDV falls to £2,430,000. Profit falls by about 60%.
Build costs 10% over, after contingencyAbout £314,30011.6%The lender does not fund overruns, so the developer must find another £126,000 in cash, mid-build.
All three: costs 10% over, three months late, prices 7.5% lowerAbout £62,6002.5%Almost all of the profit is gone, and the developer has put in £500,500.

The lesson is that development finance is cheap compared with what can go wrong. A 10% fall in sale prices costs the developer more than the entire finance bill. The figures are illustrations.

How to protect the scheme

  • Keep cash in reserve on top of the contingency, ideally enough to cover a 10% overrun and three extra months of interest.
  • Fix the build price where you can, and check what the contract lets the contractor claim for.
  • Pre-sell or pre-let some units. It reduces both the price risk and the time risk, and lenders reward it.
  • Negotiate the term with a few months’ slack, and agree the cost of an extension before you need it.
  • Line up a fallback exit, such as a bridging or development exit loan, or letting the units and refinancing.

Mezzanine finance: less cash in, more risk

Mezzanine finance lets a developer put in less of its own money by adding a second, more expensive loan behind the senior lender. It improves the return on cash when things go well and makes losses bigger when they do not.

Worked example: replacing £200,000 of equity with mezzanine

The same developer has only £174,500 rather than £374,500. A mezzanine lender provides £200,000 at 1.6% a month, rolled up, with a 2% fee. It is repaid from sales after the senior loan. The illustrative rates are assumptions, not quotes.

The six-unit scheme with and without mezzanine finance
Senior loan onlySenior plus mezzanine
Developer’s cash£374,500£174,500
Mezzanine costNoneAbout £54,800
Profit before tax, base caseAbout £440,300About £385,500
Profit as a share of the developer’s cashAbout 118%About 221%
Profit if all three things go wrongAbout £62,600A loss of about £6,300

The mezzanine cuts the profit by about £54,800 but nearly doubles the return on the developer’s cash. In the combined downside, it turns a small profit into a small loss, and the developer still has to find the £126,000 overrun.

Mezzanine works best on schemes with a wide profit margin, an experienced team and a fixed-price build. On a thin margin, an equity partner who shares the risk may be a better choice, even though it costs more of the upside. The senior lender must agree to any mezzanine loan, usually in an intercreditor agreement that sets out who is repaid first and who can step in.

Residential and commercial schemes: what changes

The structure of the loan is the same, but tax, building rules, leverage and the exit differ between homes and commercial property.

Residential and commercial development finance compared
Residential (new homes)Commercial (industrial, offices, retail)
VAT on the buildZero-rated for new homes. 5% on most conversions to homes.Usually 20%, recovered by a VAT-registered developer.
VAT on the saleFirst sale of a new home is zero-rated, so VAT on costs is usually recoverable.Standard-rated for a new building sold within 3 years, or where the developer opts to tax.
Typical leverageOften up to 65% to 70% of GDV.Often a little lower, around 60% to 65% of GDV, with higher rates.
Pre-sales and pre-letsOften not required on small schemes.More often required, especially for offices and larger units.
Warranties10-year structural warranty expected by buyers’ lenders.Collateral warranties from the contractor and professional team.
Building safetyBuilding Safety Regulator approval for buildings of 18 metres or 7 storeys with 2 or more homes.Mainstream building control in most cases.
Affordable housingCan be required on major schemes of 10 or more homes.Not applicable, but other contributions can apply.
ExitSales to home buyers, or a bulk sale or refinance of a build to rent block.Sales to owner-occupiers or investors, or let and refinanced.
Our upcoming serviceOutside it, as it excludes residential-property security.Within its scope for UK limited companies.

Mixed-use schemes, such as shops with flats above, fall between the two. Lenders and HMRC each treat them according to their own rules, so check how a lender will value and secure the residential part.

Development finance for first-time developers

First-time developers can get development finance, but the choice is narrower and the terms are tighter. Expect a lower loan to cost, a higher rate, more equity and closer monitoring. These steps make the biggest difference:

  • Start small and simple. A conversion or a handful of units with full planning, in a location with plenty of comparable sales, is much easier to fund than a first block of flats.
  • Bring in experience. An experienced project manager, an established contractor on a fixed-price contract or a joint venture with a developer who has done it before can stand in for your own track record.
  • Show relevant background. Lenders give weight to experience in construction, surveying, refurbishment or property investment, even without a completed development.
  • Put in more of your own money. A larger equity share reduces the lender’s risk and leaves room in the GDV cap.
  • Get the appraisal checked. An independent quantity surveyor’s cost plan is cheap compared with an underpriced build.

A broker who specialises in development finance knows which lenders back first-time developers. Ask how they are paid, how many lenders they work with and whether they charge you a fee.

Risks to understand before you sign

  • Contractor failure. If the contractor stops work or becomes insolvent, the programme stops but the interest does not. Check the contractor’s finances and keep a retention, and ask what the lender does if a replacement is needed.
  • Running out of facility. Overruns and delays are the developer’s problem. When the rolled-up interest reaches the facility limit, the lender may ask you to pay interest monthly or put in more cash.
  • Default terms. Missing the repayment date, or breaching a condition, can trigger default interest and fees. Read how the lender can step in, appoint a receiver or sell the site.
  • Valuation falls. A lower valuation at a later stage can cut what the lender will release, even if the build is on track.
  • Personal liability. Guarantees can make directors personally liable for some or all of the debt, and for overruns.
  • Planning and building control. Unmet pre-commencement conditions, a missed CIL notice or an unexpected building safety requirement can stop drawdowns.

A short-term loan with a hard deadline suits a developer with a clear exit and cash in reserve. It is a poor fit for a scheme that only works if everything goes to plan.

Applying for development finance: ten steps

  1. Secure the site properly. An option, a conditional contract or an agreed purchase, with time for planning and funding.
  2. Confirm planning. Full permission, the conditions and their timing, and whether CIL, section 106 or BNG apply.
  3. Price the build. A cost plan from a quantity surveyor and, ideally, a fixed-price tender from a contractor with sound accounts.
  4. Price everything else. Utilities, fees, warranties, VAT cash flow, sales costs and a realistic contingency.
  5. Prove the value. Comparable sales or lettings and agents’ written views on price and speed of sale.
  6. Build the appraisal and stress-test it. Cost overruns, delays and lower prices, alone and together.
  7. Set up the SPV and show your equity. Where your cash is and when it goes in.
  8. Compare terms in pounds. Facility size, the share of the site funded, rate, every fee, term, extension costs and guarantees.
  9. Plan the exit and the fallback. The sale or refinance, who will lend on it and what happens if it is late.
  10. Read the facility letter with your solicitor. Conditions before each drawdown, events of default, step-in rights and every guarantee.

For a let commercial building, the commercial mortgage calculator shows what a refinance would cost each month. Our guides on getting a commercial mortgage and the borrowing checklist cover the preparation that applies to any property loan.

Common questions

What is development finance?

Development finance is a short-term loan for building new property or carrying out a major conversion or refurbishment. It is released in stages as the work is done and checked, interest is usually rolled up, and the loan is repaid from the sale or refinance of the finished property.

How does development finance work?

The lender funds part of the site purchase on day one, then releases money for the build each month, in arrears, after a monitoring surveyor certifies the work. Interest is added to the balance. When the building is finished, sale proceeds or a refinance repay the loan, interest and fees.

How much deposit do I need for development finance?

Usually 10% to 25% of the total project cost, depending on the lender, your experience and the scheme’s profit. Lenders commonly fund 75% to 90% of costs, capped at 60% to 70% of the finished value. Mezzanine or an equity partner can reduce your share further, at a cost.

What are development finance rates in 2026?

In October 2026, senior development loans are typically priced at about 0.65% to 1.1% a month, roughly 8% to 13% a year, with Bank Rate at 3.75%. Expect an arrangement fee of 1% to 2%, an exit fee of up to about 1.5%, and valuation, legal and monitoring costs on top.

What is GDV in development finance?

GDV, or gross development value, is the expected market value of the finished scheme, usually the total of all the unit sale prices. Lenders cap the loan at a percentage of GDV, often 60% to 70%, and value it through an independent RICS valuer.

What is the difference between loan to cost and loan to GDV?

Loan to cost compares the loan with the total cost of the project, while loan to GDV compares it with the finished value. Lenders set a limit on each and lend the lower amount. On a scheme with a modest profit, the GDV limit is usually the one that applies.

Can I get development finance with no experience?

Yes, but from fewer lenders and on tighter terms. Start with a small, simple scheme with full planning, use an experienced contractor on a fixed-price contract and a project manager, put in more of your own money, or partner with an experienced developer.

Can development finance cover 100% of costs?

Rarely from a single lender. Senior lenders stop at about 90% of costs. Combining senior debt with mezzanine can reach about 95%, and an equity partner can provide the rest, but each layer takes a share of the profit and makes losses bigger.

How long does development finance take to arrange?

Usually 6 to 12 weeks from application to the first drawdown, covering the valuation, the monitoring surveyor’s initial report, credit approval and legal work. Schemes with planning conditions still to discharge or unusual property can take longer.

What is a monitoring surveyor?

A quantity surveyor appointed by the lender, and paid for by the borrower, who reviews the build contract and costs before the loan starts and visits the site, usually monthly, to certify work before each drawdown. They report to the lender, not to you.

Is development finance regulated?

Development finance for a limited company building property to sell or let is not a regulated mortgage contract, so FCA mortgage rules do not apply. Loans to individuals for a home they will live in can be regulated. Read the facility letter carefully and take legal advice.

Do I need planning permission to get development finance?

For a development loan, yes. Most lenders want full planning permission and a clear plan for the conditions before they fund the build. Before planning, a site can sometimes be bought with a bridging loan based on its current value, with the planning risk resting on you.

What happens if my development overruns?

Lenders do not usually fund cost overruns, so the developer must pay them. If delays push the rolled-up interest past the facility limit, you may have to pay in more cash, pay interest monthly or agree an extension, often at a higher rate and with a fee.

What is the difference between development finance and a bridging loan?

Both are short-term property loans. A bridging loan is usually paid out in one go against a property’s current value. Development finance is drawn down in stages to fund a build and is sized on the cost and the finished value.

From working it out to moving forward

Company finance.
Register your interest.

We’re preparing direct lender introductions for UK limited companies. No lenders are confirmed yet. Register your interest and we’ll email you about launch; we cannot currently obtain quotes or make introductions.

  • Built around your request. Start with the finance type and amount you need.
  • Email comes first. Receive a confirmation and updates about the launch of the company-only service.
  • You decide. Registering interest is not a finance application. There’s nothing to pay us.

You never pay us. Once our lender service launches, if you go ahead with finance through an introduction, the lender may pay us a commission. Business Loan Advice is not a lender and doesn’t give regulated advice. We’ll confirm any introduction with you before sharing your details. A request is not an application or a guarantee of an offer.

Register your company’s interest

Enter one amount in pounds, for example 50000.

8 characters, including leading zeros. For example, 11832035 or SC123456.

Add anything else (optional)

No obligation. Free for you. No credit search by Business Loan Advice.

Register interest